Nevada Department of Transportation |
|
|
Request For Information |
No. 9 |
|
|
NDOT Contract
Data |
NDOT Contact
Data |
PROJECT: EB-NH-095-2(046) |
CONTACT PERSON: JonDickinson |
CONTRACT NO. 3326 |
TELEPHONE: 775-888-7560 |
|
FAX: |
|
|
Contractor
Data |
|
TRANSDYN INC |
CONTACT PERSON: MICHAEL RICKETTS |
5669 GIBRALTER DRIVE |
TELEPHONE: 925-225-1600 |
PLEASONTON, CA 94588 |
FAX: 925-225-1610 |
|
EMAIL: rboardman@transdyn.com |
|
TOPIC: Misc Questions |
QUESTION: 2/5/2007
10:52:00 AM |
Section 105.03 (a) (E): Please clarify the following; Please define
the “NDOT communication software” to be used to test the communications
protocols and interfaces to the new field devices including the protocols
and interfaces required and provided, the functionality supported and the
hardware requirements to run the software. Please explain the requirement
to operate active field devices on an “interim” basis. Please explain the
statement that “the two functional elements of device communications
software may be combined into one package or delivered as 2 separate
software packages with respect to the integrations requirements that might
arise accordingly. Please explain what changes to the NDOT test
communications software are anticipated and that NDOT is responsible for
implementing those changes. Will changes to the communications test
software require changes to the operating system software and is NDOT
responsible for those changes as well? Section 105.03 (a) (F): Please
clarify the following; Is the “FAST Central System Software device
communication software developed for the SST loaded on the NDOT furnished
operator workstation located at the TMC” is the same test communications
software provided by NDOT in Section 105.03(a)(E) above. Section
623.01.02: Please clarify the following; k: Does NDOT required a Systems
Engineer be assigned to the field for the life of the contract or only for
the period of field integration? Does this include the Availability Test
and Warranty period? Section 623.02.23 Controllers: Please clarify the
following; Please define the NDOT owned firmware to be used in the 170E
Controllers. Please define the “computers being furnished to the project”
for SST testing. Please define the communications protocol required for
the controllers, the radar detectors, and the VIDS. Please define the
functional requirements for radar detectors, VIDS and ramp metering.
Section 623.02.28, Video Image Detection System: Please clarify the
following: Please define the technical and functional requirements for
this equipment. Please define the interface of this equipment to the FAST
central system. Section 623.02.33, CCTV Field Equipment: Please clarify
the following; Please specify brand and model of existing CCTV field
equipment. Section 623.02.34, Dynamic Message Sign: Please confirm the
following; Please define the protocol required to be used to communicate
between the DMS and the central system. Is the existing system NTCIP
compliant? Section 623.02.38, Modify Traffic Management Center: Please
clarify the following; Please clarify if NDOT requires modification of its
existing IT software in order to integrate system components with FAST
FMS. Please fully describe the existing FAST FMS software that will
require modification. Please describe all required upgrades to existing
FAST FMS software required by NDOT. Please describe all new licensing of
new applications or upgrades to existing applications. Section 623.02.42,
Note Processor: Please clarify the following; Please provide the
functional, interface, and physical characterizes of this device to be
installed by the systems integrator. The Contract Drawings include the
following equipment as to be supplied by the systems integrator, however,
the specifications do not include any functional or technical
specifications for these items. Please clarify the requirements for: FMS
Server Computer Operator Workstation Computer Operator Workstation Video
Monitor FMS Video Graphics Computer Wall Processor Network Management
Computer and associated Network Switch The Contract Drawings show a
Central Video Switch to be upgraded by the systems integrator. Please
provide information on the make, model and upgrade required by NDOT.
|
|
RESPONSE: 2/12/2007
11:59:00 AM |
Section 105.03 (a)(E): Please clarify the following; Please define
the “NDOT communication software” to be used to test the communications
protocols and interfaces to the new field devices including the protocols
and interfaces required and provided, the functionality supported and the
hardware requirements to run the software. Response: The software was
developed by the FAST stage 1 System Integrator as a way to test field
devices installed on that project. The Department will supply that
software “as is” to the Contractor/System Integrator who is awarded this
project for their use. The Department makes no claim to its worthiness to
the Contractor/System Integrator. Please explain the requirement to
operate active field devices on an “interim” basis. Response: Until the
devices are tied into the FAST Central System Software. The System
Integrator may use the “NDOT” Communication software to test the
equipment/system. Please explain the statement that “the two functional
elements of device communications software may be combined into one
package or delivered as 2 separate software packages with respect to the
integrations requirements that might arise accordingly. Response: This
wording was mistakenly left in the special provisions. The Department will
provide you with test software used during previous system acceptance
testing. The device communication software that NDOT currently has may
need to be modified based on equipment selection by the Contractor/System
Integrator. The Contractor/System Integrator is responsible for any and
all modification needed in order to perform the required testing on this
project. Please explain what changes to the NDOT test communications
software are anticipated and that NDOT is responsible for implementing
those changes. Will changes to the communications test software require
changes to the operating system software and is NDOT responsible for those
changes as well? Response: It is unknown what if any modifications are
needed. The Department will provide you with testing software used during
previous system acceptance testing. The device communication software that
the Department currently has may need to be modified based on equipment
selection by the Contractor/System Integrator. The Contractor/System
Integrator is responsible for any and all modification needed in order to
perform the required testing on this project. NO CHANGES TO THE FAST
CENTRIAL SYSTEM SOFTWARE WILL BE ALLOWED. Section 105.03 (a) (F): Please
clarify the following; Is the “FAST Central System Software device
communication software developed for the SST loaded on the NDOT furnished
operator workstation located at the TMC” is the same test communications
software provided by NDOT in Section 105.03(a)(E) above. Response: No, the
Department will provide you with test software used during previous system
acceptance testing that can be used for the SST testing. The
Contractor/System Integrator is required to use the FAST Central System
Software for the SAT Testing. Section 623.01.02: Please clarify the
following; k: Does NDOT required a Systems Engineer be assigned to the
field for the life of the contract or only for the period of field
integration? Does this include the Availability Test and Warranty period?
Response: The Systems Engineer shall be on site through system acceptance.
The Systems Engineer is not required to be in site during the warranty
period. Section 623.02.23 Controllers: Please clarify the following;
Please define the NDOT owned firmware to be used in the 170E Controllers.
Response: The Department, on an earlier phase of the FAST Project has
developed the firmware required for the detector stations and ramp meters.
The Contractor/System Integrator is required to use that firmware. Please
define the “computers being furnished to the project” for SST testing.
Response: The Department will allow the Contractor/Systems Integrator
access to one operator workstation at the TMC for the SST testing. Please
define the communications protocol required for the controllers, the radar
detectors, and the VIDS. Response: The communications protocol is the same
protocol used on earlier FAST contracts and is available upon request. No
changes will be allowed. Please define the functional requirements for
radar detectors, VIDS and ramp metering. Response: The communications
protocol is the same protocol used on earlier FAST contracts and is
available upon request. No changes will be allowed. Section 623.02.28,
Video Image Detection System: Please clarify the following: Please define
the technical and functional requirements for this equipment. Please
define the interface of this equipment to the FAST central system.
Response: The Video Image detection System is used for vehicle detection
on the ramp meters. Acceptable video image detection systems are Iteris
Edge 2 with 1 mouse and 1 monitor in each ramp meter cabinet and Iteris
Cameras or Autoscope Rackvision with 1 mouse and 1 monitor in each ramp
meter cabinet and Autoscope cameras. No other systems will be accepted
Section 623.02.33, CCTV Field Equipment: Please clarify the following;
please specify brand and model of existing CCTV field equipment. Response:
Cohu’s IVIEW camera utilizing the FAST CCTV Protocol. The specifications
allow for other cameras as long as they meet the requirements of the
special provisions. Section 623.02.34, Dynamic Message Sign: Please
confirm the following; please define the protocol required to be used to
communicate between the DMS and the central system. Is the existing system
NTCIP compliant? Response: Supply only DMS’s that are on NDOT’s Qualified
Products List. The signs on the QPL meet all the NDOT protocol
requirements and NTCIP requirements. No other DMS’s will be accepted.
Section 623.02.38, Modify Traffic Management Center: Please clarify the
following; please clarify if NDOT requires modification of its existing IT
software in order to integrate system components with FAST FMS. Please
fully describe the existing FAST FMS software that will require
modification. Please describe all required upgrades to existing FAST FMS
software required by NDOT. Please describe all new licensing of new
applications or upgrades to existing applications. Response: No
modifications are needed are will be permitted on the FAST Central System
Software (FAST FMS). As the system is expanded on this contact, equipment
at the TMC may need to be upgraded or expanded. The System Integrator is
responsible for any and all upgrades and/or modifications needed to make a
fully functioning TMC utilizing NDOT’s FAST Central System Software. This
contract is for expansion of NDOT’s FAST System. The System Integrator
need only supply the additional hardware associated with the new devices
being added to the system. This bid item also includes all the labor
associated with installing that additional equipment, connecting, testing
and making fully operational all new and existing field elements within
the project limits. Section 623.02.42, Note Processor: Please clarify the
following; Please provide the functional, interface, and physical
characterizes of this device to be installed by the systems integrator.
The Contract Drawings include the following equipment as to be supplied by
the systems integrator, however, the specifications do not include any
functional or technical specifications for these items. Response: The Node
Processor will be supplied and by the Department. The System Integrator is
responsible for the installation and testing of that equipment. A cut
sheet of this device is available on request. The Node Processor will be
supplied with software installed, Please clarify the requirements for: FMS
Server Computer Operator Workstation Computer Operator Workstation Video
Monitor FMS Video Graphics Computer Wall Processor Network Management
Computer and associated Network Switch Response: The above list of
equipment is already installed and operational at the TMC. Cut sheet of
this device is available on request. The Contract Drawings show a Central
Video Switch to be upgraded by the systems integrator. Please provide
information on the make, model and upgrade required by NDOT. Response: The
Central Video Switch was upgraded on a previous NDOT contract and will
have the required inputs available for the Contractor/System Integrator to
use on this contract. A walk-thru can be scheduled for the TMC upon
Request. |